EXTREME CABLE MANAGEMENT

Latest Projects

Azerbaijan

Shah Deniz Phase 2

Shah Deniz Phase 2
Year
2014 - 2016
Client
BP
Contractor
BP

The Shah Deniz Field is located approximately 90km offshore in the Azerbaijan sector of the South Caspian Sea, in water depths ranging from 50m to 500m. It is a high pressure, sweet gas condensate field, with estimated reserves of nearly 1 trillion cubic metres of gas and 2.4 billion barrels of condensate.

Production from the Shah Deniz Field commenced at the end of 2006, with the initial development known as Shah Deniz Stage 1 (SD1), which incorporated an 8.6 bcma capacity output from a platform located in the NE portion of the field and a new onshore terminal at Sangachal.

The Shah Deniz Stage 2 development (SD2), will result in the installation of a further 16 bcma capacity and will build on SD1 to develop the remaining gas resource. This will be accompanied by a major extension to the onshore terminal and the expansion of the existing South Caucasus Pipeline (SCP) to carry the additional sales gas to the Georgia-Turkey border. First gas from SD2 is anticipated in 2018. The overall cost of the project will be in the region of $20bn.

Vantrunk are supplying the Speedway SW4 & SW6 Cable Ladder system, Heavy Duty Cable Tray system and Intelok Steel Framing system directly to BP. This follows on the back of Vantrunks successful working relationship with BP in Azerbaijan over the previous 12 years.  

UK

Alder Project

Alder Project
Year
2014 - 2015
Client
Dron & Dickson
Contractor
AMEC

Alder is a high-pressure and high-temperature gas condensate field located in Block 15/29a of the UK Continental Shelf. The field lies in a water depth of 492ft (150m) in the central North Sea, approximately 100 miles away from the Scottish coastline and 37 miles away from the UK / Norway median line.

Alder will be developed as a satellite of the operating Britannia field, located 27km east of it in block 16/26. The offshore project is owned by the operator Chevron (73.68%) and Conoco Phillips (26.32%).

Vantrunk supplied the Speedway SW5 Cable Ladder system and Intelok Steel Frming system through Vantrunk's Aberdeen distributor, Dron & Dickson. 

UK

Murchison Decommissioning Project

Murchison Decommissioning Project
Year
2014 - 2015
Client
Dron & Dickson
Contractor
Aker Solutions

As a prudent and responsible operator, CNR International (U.K.) Limited (CNRI) initiated the planning for the decommissioning of the Murchison field in the UK sector of the North Sea in 2010. Cessation of production took place according to plan on 28 February 2014.

The decommissioning of Murchison has now begun with the engineering-down and cleaning of the platform and the campaign to plug and abandon the oil wells in the Murchison field well underway.

Vantrunk were chosen by Aker Solutions to supply the required Cable Management and suports to facilitate the decommissioning programme and have supplied the Speedway SW5 & SW6 in both a galvanised and stainless steel finish. The products were supllied through Vantrunk's distributor in Aberdeen, Dron & Dickson. 

Ghana

TEN Development Project

TEN Development Project
Year
2014 - 2015
Client
Eutex Pacific
Contractor
SOFEC

The TEN development project includes the collective development of three hydrocarbon accumulations - Tweneboa, Enyenra (formerly, Owo) and Ntomme. The three oil and gas fields are part of the Deepwater Tano license located offshore of Ghana.
The fields lie in water depths of 1,000m to 2,000m. The development is located 25km away from the Tullow-operated Jubilee field. It is the first deepwater field to be developed in offshore Ghana.

The three accumulations will be developed together in an integrated development scheme through a single FPSO. The
FPSO will be moored in 1,500 metres of water and will be capable of handling expected plateau production of 80,000 b/d of oil, 65,000 of produced water, and 180 MMcf/d of gas, with an onboard storage capacity of 1.7 million barrels of total fluids.

Vantrunk supplied the Speedway SW6 Cable Ladder system Heavy Duty Cable Tray system in stainless steel through our distributor in Singapore, Eutex Pacific. 

Iraq

Majnoon

Majnoon
Year
2014 - 2015
Client
Foster Wheeler Kentz
Contractor
Sheel

Majnoon oil field is a super-giant oil field located 60 km from Basra, Basra Governorate in southern Iraq. Majnoon is one of the richest oil fields in the world with an estimated 38 billion barrels of oil in place.

In 2009, following Iraq's second licensing round for oil production, the government signed a 20-year service contract with international oil companies Shell and Petronas to develop the Majnoon oilfield. The Majnoon field measures around 60 kilometres long and 15 kilometres wide and is estimated by the Iraqi government to hold around 38 billion barrels of oil in place. Shell is the lead operator in the consortium with a 45% stake, Petronas holds 30% and the Iraqi South Oil Company the remaining 25%.

Vantrunk have been chosen to supply the Speedway SW6 Cable Ladder system and Heavy Duty Cable Tray system in Vantrunks Extreme Steel with a Hot Dipped Galvanised finish. Vantrunk have supplied various phases of the project through Maclean Electrical in Dingwall, Rexel IPG London and R&M Southampton.

Brazil

Petrobras P75 & P77

Petrobras P75 & P77
Year
2014 - 2015
Client
QGI
Contractor
Petrobras

FPSOs (platforms that produce, store and offload oil) P-75 and P-77, with production capacities of 150,000 barrels per day each, will be deployed in Transfer of Rights blocks, in the Santos Basin pre-salt layer, along with two other similar units, the P-74 and P-76. The RIG Consortium will be in charge of building the modules of and integrating both platforms. The work will be done at the Honorio Bicalho shipyard, in Rio Grande.

The vessels intended to have their hulls converted to the P-75 and P-77 are at the Cosco Shipyard, in China, undergoing hull preparation services, and are expected to arrive in Rio de Janeiro (RJ) in the second half of 2014, where the conversion works will be performed at the Inhauma Shipyard. Upon the completion of this step, the hulls will go to Rio Grande. The P-75 is slated to arrive in Rio Grande in the second half of 2015, while the P-77 in the first half of 2016. The works are expected to create approximately 4,400 direct and indirect jobs at the peak of activities. The contractual domestic content is foreseen to be 65% to 71%.

Vantrunk are supplying the Speedway SW6 Cable Ladder system and Heavy Duty Cable Tray system in marine grade stainless steel. The project is being supplied in conjunction with Vantrunk local agent Polar. 

UK

Songa Endurance

Songa Endurance
Year
2015
Client
Songa Drilling
Contractor
Dron & Dickson

The Songa Endurance is a sixth generation, high specification, harsh environment, midwater rig designed for year around drilling, completion, testing and intervention operations in water depths up to 500 meters.

The rig is certified DP3 and is equipped with a drill-floor and an efficient layout with improved safety and working environment features. Songa Endurance is the second rig in a series of four Category D rigs specifically built for and contracted to Statoil. Songa’s first CAT D rig, the Songa Equinox, was delivered in June 2015.

Australia

Gorgon LNG

Gorgon LNG
Year
2012 - 2014
Client
TSG Consortium
Contractor
Chevron / KJVG Consortium

Development proposal includes establishment of an LNG facility on Barrow Island, which lies directly between the gas fields and the mainland.
LNG plant will have three trains with a nominal capacity of 5 million tonnes per annum each (Train 1 due online 2014). The LNG plant can only be 300 hectares big under the 2003 Barrow Island Act.

Vantrunk supplied Speedway Cable Ladder (SW6) and Cable Tray (HR).

Australia

Greater Gorgon LNG Project

Greater Gorgon LNG Project
Year
2012 - 2014
Client
TSG Consortium
Contractor
Chevron / Laing O'Rourke

Development proposal includes establishment of an LNG facility on Barrow Island, which lies directly between the gas fields and the mainland.

LNG plant will have three trains with a nominal capacity of 5 million tonnes per annum each (Train 1 due online 2014). The LNG plant can only be 300 hectares big under the 2003 Barrow Island Act.

Vantrunk supplied Speedway Cable Ladder (SW6) and Cable Tray (HR).

Australia

Greater Gorgon LNG Project HHI

Greater Gorgon LNG Project HHI
Year
2011 - 2014
Client
TSG Consortium
Contractor
Chevron / KJVG Consortium

Development proposal includes establishment of an LNG facility on Barrow Island, which lies directly between the gas fields and the mainland.

LNG plant will have three trains with a nominal capacity of 5 million tonnes per annum each (Train 1 due online 2014). The LNG plant can only be 300 hectares big under the 2003 Barrow Island Act.

Vantrunk supplied Speedway Cable Ladder (SW6) and Cable Tray (HR).

UK

Cygnus

Cygnus
Year
2013 - 2014
Client
Maclean Electrical
Contractor
Amec / GDF Suez

Vantrunk as a sub-supplier to MacLean Electrical have been awarded a major contract to supply their world renowned Speedway Cable Ladder system to the GDF SUEZ E&P UK operated Cygnus Gas Project. Vantrunk will supply their Speedway SW6 Ladder complete with accessories in marine grade stainless steel to ensure the system can withstand the harsh North Sea environment. The award cements Vantrunk’s position as the leader in Extreme Cable Management.

The Cable Ladder will be manufactured out of Vantrunk’s 100,000 sq ft facility in Warrington and shipped to Heerema Fabrication Group’s Hartlepool yard in the United Kingdom where fabrication and commissioning of four topsides is taking place.

The Cygnus project, sanctioned in August 2012, is expected to contribute 5% to UK gas production at peak production (due 2016) – supplying gas to the equivalent to 1.5 million homes in Britain. GDF SUEZ E&P UK is the operator of Cygnus, responsible for ensuring that this valuable hydrocarbon resource is extracted and supplied safely and efficiently. Cygnus gas field is situated in the Southern North Sea within UK Continental Shelf blocks 44/12a and 44/11a in 23m of water 

UK

Greater Stella Area Development

Greater Stella Area Development
Year
2013 - 2014
Client
Petrofac
Contractor
Petrofac / Ithaca

Vantrunk are delighted to announce the award of a contract from Petrofac for supply of the Speedway SW6 Cable Ladder system and Heavy Duty Cable Tray system in 1.4404 grade stainless steel. The award of this contract cements Vantrunk's positive working relationship with Petrofrac both in the UK and internationally. 

The Stella and Harrier fields will be developed via subsea tieback to the FPF1 vessel. First oil from the hub is forecast at an initial annualised average rate of 30,000 barrels of oil equivalent per day. 

Petrofac’s Offshore Engineering & Operations business will carry out modification and upgrade works to the FPF1 ahead of its deployment on the Greater Stella Area development. Petrofac will subsequently provide Duty Holder services to the FPF1 on a life of field contract. In accordance with its standard accounting policy, Petrofac will book the initial five years' of estimated contract revenues into backlog in relation to the upgrade and Duty Holder contracts, which equates to US$540 million.

Brazil

P58 Baleia Azul Field

P58 Baleia Azul Field
Year
2011 - 2013
Client
CQG Oil & Gas Contractor INC. via Polar
Contractor
Petrobras

Vantrunk are delighted to announce the award of two prestigious contracts from CQG Oil & Gas Contractor INC. & CCI Oil & Gas Contractor INC. for the supply of steel cable management products to the Petrobras P-58 & P-62 FPSOs.

The P-58 will be deployed on the Baleia Azul field and is intended to produce up to 180,000 barrels per day and will have a gas compression capacity of 6 million cubic metres per day. The P-62 will be deployed on the Roncador field in 1800m of water and will have the capacity to produce 180,000 barrels per day and 6 million cubic metres per day of natural gas production capacity. Vantrunk will be supplying their world renowned Speedway® SW4 & SW6 Cable Ladder systems as well as their Heavy Duty Cable Tray system.

Vantrunk are looking forward to working closely with CQG Oil & Gas Contractor INC. & CCI Oil & Gas Contractor INC. throughout the duration of these projects and are delighted to have the opportunity to build on their experience in the Brazilian market following the previous successful supply to the Petrobras P-55 project in 2009/10

Brazil

P62 Roncador Field

P62 Roncador Field
Year
2011 - 2013
Client
CCI Oil & Gas Contractor INC. via Polar
Contractor
Petrobras

Vantrunk are delighted to announce the award of two prestigious contracts from CQG Oil & Gas Contractor INC. & CCI Oil & Gas Contractor INC. for the supply of steel cable management products to the Petrobras P-58 & P-62 FPSOs.

The P-58 will be deployed on the Baleia Azul field and is intended to produce up to 180,000 barrels per day and will have a gas compression capacity of 6 million cubic metres per day. The P-62 will be deployed on the Roncador field in 1800m of water and will have the capacity to produce 180,000 barrels per day and 6 million cubic metres per day of natural gas production capacity. Vantrunk will be supplying their world renowned Speedway® SW4 & SW6 Cable Ladder systems as well as their Heavy Duty Cable Tray system.

Vantrunk are looking forward to working closely with CQG Oil & Gas Contractor INC. & CCI Oil & Gas Contractor INC. throughout the duration of these projects and are delighted to have the opportunity to build on their experience in the Brazilian market following the previous successful supply to the Petrobras P-55 project in 2009/10

Oman

Mukhaizna Gas Field Oman

Mukhaizna Gas Field Oman
Year
2013
Client
Oilfields Supply Center
Contractor
Occidental Petroleum Corporation

Vantrunk are delighted to announce the award of a large contract to supply 18km of Speedway Cable Ladder (SW6) complete with covers and accessories to Occidental in Oman. The contract was secured through our agents in Oman Oilfields Supply Centre and follows on the back of a similar order from Occidental which was completed in December 2012. The Speedway Cable Ladder features a fully slotted sidewall, unique sidewall profile and patented coupling pattern all of which are designed to maximise strength and minimise installation time. The Speedway Ladder will be manufactured from Vantrunk’s Extreme Steel which has a yield strength of 275 N/mm thus increasing the loading capability of the cable management system and providing potential savings in support steel work.

Oxy’s Oman operations are concentrated at the Mukhaizna Field in south-central Oman, and the Safah and Wadi Latham fields and Block 62 in northern Oman. During its more than 30-year tenure in Oman, Oxy has increased production and reserves, and today is one of the country’s largest oil producers. At the Mukhaizna Field, Oxy has implemented an aggressive drilling and development program, including a major pattern steam flood project for enhanced oil recovery. To produce feed water for the steam needed for the project, non-potable water from multiple sources, such as water separated from oil production, is conditioned using various technologies — including the largest mechanical vapour compressors ever built
 

Brazil

FPSO Cidade de Ilhabela - Veolia Water Treatment Plant

FPSO Cidade de Ilhabela - Veolia Water Treatment Plant
Year
2013
Client
Rexel IPG
Contractor
Veolia / SBM

Supply of Vantrunk's Speedway SW6 Cable Ladder system and Heavy Duty Cable Tray system in 1.4404 marine grade stainless steel via Rexel IPG. The Cidade de Ilhabela will be used in the north part of Sapinhoá field (former Guara Area) development in the pre-salt area offshore Brazil. 

Brazil

Cidade de Maricá and Cidade de Saquarema - Veolia Water Treatment Plant

Cidade de Maricá and Cidade de Saquarema  - Veolia Water Treatment Plant
Year
2013
Client
Rexel IPG
Contractor
Veolia / SBM

Supply of Vantrunk's Speedway SW6 Cable Ladder system and Heavy Duty Cable Tray system in 1.4404 marine grade stainless steel via Rexel IPG. The Cidade de Marica & Saquarema are destined for the Lula field in the pre-salt province offshore Brazil. BM-S-11  block is under concession to a consortium comprised of PETROBRAS (65%), BG E&P Brasil Ltda. (25%), and Petrogal Brasil S.A. (10%). 

UK

Nexen Golden Eagle

Nexen Golden Eagle
Year
2012 - 2013
Client
Nexen
Contractor
CB&I / Lamprell

Nexen Petroleum's Golden Eagle Area Development (GEAD) project includes development of the Golden Eagle and Peregrine (formerly Pink) fields.

The GEAD project was approved by the UK Department of Energy and Climate Change in October 2011. It is being executed by the operator, Nexen, holding a 36.5% interest. Partners include Maersk Oil North Sea (31.56%), Suncor Energy (26.69%) and Edinburgh Oil and Gas (5.21%).

Vantrunk supplied the Speedway SW6 Cable Ladder system direct to Nexen as part of a framework agreement established for the project. 

Brazil

Petrobras P-55 Seisub Platform

Petrobras P-55 Seisub Platform
Year
2009 - 2012
Client
Petrobras
Contractor
Quip SA via Polar

The P55 Vessel is being built in Brazil by the Quip Consortium which is made up of three Brazilian contractors Queiroz Galvao, IESA and UTC Engenharia. The consortium set up in 2005 had previously built the P-53 FPSO for Petrobras and through successful bidding against an international consortium was awarded the contract to build and install the 22,000 tonne topside and integration modules for the giant P55 vessel. The P55 Semi Submersible forms part of the 3rd Phase of the Roncador Development Project situated 125km off the coast of Sao Tome Cape in the Brazil’s maturing Campos Basin.

Vantrunk offered Quip a competitive bid package which encompassed Speedway Cable Ladder, Vantrunk Cable Tray Systems and Supporting Brackets & Accessories. In late 2009, Vantrunk demonstrated its position as an international market leader of cable management systems by successfully supplying the cable management solutions to the P-55 Semi Submersible Platform. Vantrunk has been working very closely with Quip over the duration of the project and will carry on as the project proceeds further.

Qatar

Gas Sweetening Facilities (GSF) at Mesaieed & Dukhan

Gas Sweetening Facilities (GSF) at Mesaieed & Dukhan
Year
2011 - 2012
Client
Petrofac
Contractor
Qatar Petroleum / Petrofac

The plant will have the capacity to process around 750 million cf/d of gas which will be used as feedstock for petrochemicals capacity planned at Masaieed.
It will include a new acid gas removal unit, amine sweetening plant, rehabilitation of the sulphur recovery unit, supply and installation of compressors, a seawater cooling system, dehydration unit & flare gas system.

Vantrunk supplied Speedway Cable Ladder (SW5) and Cable Tray (HR)

Abu Dhabi

Gasco/IGD/LPG Storage Tanks

Gasco/IGD/LPG Storage Tanks
Year
2011 - 2012
Client
Abu Dhabi Gas Industries Limited (GASCO)
Contractor
CB&I (Supplied through Eutex International)

The new storage tanks will be added to the existing storage tanks to increase storage capacity for propane, butane and paraffinic naphtha products.

The new tanks will be interconnected with the Train 1, 2 and 3 product rundown, loading and shipping network so that the contents of any tank can be shipped from any of the berths. There will be 3 refrigerated Propane Tanks and 3 refrigerated Butane Tanks.

Vantrunk supplied Speedway Cable Ladder (SW4 & SW6) and Cable Tray (HR).

FINISHES & MATERIALS :
Structural grade carbon steel with a deep
hot dipped galvanised finish.


SPECIAL FEATURES:
The use of a specialised steel enabled an
enhanced galvanising coating which will
prolong the time to first maintenance and
the overall lifespan of the product.

Singapore

OSX 3

OSX 3
Year
2012
Client
Eutex Pacific PTE
Contractor
SOFEC

Vantrunk, in partnership with Eutex International, have successfully completed supply of our SW6 Speedway Cable Ladder System and Heavy Duty HR Cable Tray system for the OSX-3 FPSO turret mooring system being supplied by SOFEC. The OSX-3 FPSO will be utilized within block BM-C-39 of the Campos Basin, offshore Brazil, on the Tubarão Martelo field. The Speedway Cable Ladder system features fully slotted sidewalls, a unique profile design and integral coupler, all of which help save weight and speed up installation.

ABOUT OSX
OSX is a Brazilian publicly traded corporation that provides solutions for the offshore oil and natural gas industry, by means of integrated operations in shipbuilding, leasing of E&P units and O&M services. Currently, OSX is managing a broad and diversified order book of FPSOs, fixed platforms, special vessels and oil tankers. Since July of 2011, OSX has been building the Açu Shipbuilding Unit (“UCN Açu”), which will be the largest shipyard in the Americas, at the Açu Superport Industrial Complex, located in the São João da Barra Industrial District (RJ), with technology from its partner Hyundai Heavy Industries, the global leader in naval construction. For the implementation of its projects, OSX has already raised more than US$4.7 billion in funding from the financial and capital markets via its IPO, financing and bonds in the international markets. OSX is a part of the EBX Group, a corporate conglomerate founded and headed by Brazilian entrepreneur Eike Batista, who has a proven track record of successfully developing new ventures in the fields of natural resources and infrastructure, with the highest technology and sustainability standards. For more information, please visit: www.osx.com.br/ri

Singapore

SPT Plant Singapore

SPT Plant Singapore
Year
2012
Client
Shaw Group
Contractor
Eutex

The project is located at and integrated with the existing Singapore Chemical Plant on Jurong Island, providing feedstock, operating and investment synergies with both the chemical plant and the Singapore Refinery.

he project will employ ExxonMobil’s latest proprietary technologies and will produce a range of high value products to meet growing demand. The technology to produce high value products, including Vistamaxx™ specialty elastomers and Exceed™ polyethylene will be used for the first time by ExxonMobil in Asia.

Australia

Greater Gorgon LNG Project CB&I

Greater Gorgon LNG Project CB&I
Year
2011 - 2012
Client
TSG Consortium
Contractor
Chevron / CB&I

Development proposal includes establishment of an LNG facility on Barrow Island, which lies directly between the gas fields and the mainland.

LNG plant will have three trains with a nominal capacity of 5 million tonnes per annum each (Train 1 due online 2014). The LNG plant can only be 300 hectares big under the 2003 Barrow Island Act.

Vantrunk supplied Speedway Cable Ladder (SW6) and Cable Tray (HR).

China

CNOOC Tower Yoke

CNOOC Tower Yoke
Year
2012
Client
Eutex Pacific PTE
Contractor
CNOOC / SOFEC

SOFEC designed and provided project management for a tower yoke mooring system for a new 172,000 dwt purpose-built double-hull vessel. CNOOC’s nominated fabrication and installation contractor was China Offshore Oil Engineering Corporation (COOEC).

The tower yoke mooring system is located in the QHD32-6 field development in Bohai Bay China, in a water depth of 20m. The FPSO generates and provides medium voltage electrical power to six fixed unmanned satellite platforms. The medium voltage power transmission to the platforms is achieved through a medium voltage slipring assembly mounted on the rotating tower topsides module.

Australia

Greater Gorgon LNG Project Jetty

Greater Gorgon LNG Project Jetty
Year
2011 - 2012
Client
TSG Consortium
Contractor
Chevron / Saipem Spa

Development proposal includes establishment of an LNG facility on Barrow Island, which lies directly between the gas fields and the mainland.

LNG plant will have three trains with a nominal capacity of 5 million tonnes per annum each (Train 1 due online 2014). The LNG plant can only be 300 hectares big under the 2003 Barrow Island Act.

Vantrunk supplied Speedway Cable Ladder (SW6) and Cable Tray (HR).

Oman

Occidental Gas Field

Occidental Gas Field
Year
2012
Client
Oilfields Supply Center
Contractor
Occidental Petroleum Corporation

At the Mukhaizna Field, Oxy has implemented an aggressive drilling and development program, including a major pattern steam flood project for enhanced oil recovery. To produce feed water for the steam needed for the project, non-potable water from multiple sources, such as water separated from oil production, is conditioned using various technologies — including the largest mechanical vapor compressors ever built.

Vantrunk supplied our world renowned Speedway Six SW6 Cable Ladder System in a Hot Dipped Galvanised Finish. 

Singapore

Singapore Parellel Train (SPT) Project Phase 1 & 2

Singapore Parellel Train (SPT) Project Phase 1 & 2
Year
2009 - 2011
Client
ExxonMobil
Contractor
Foster Wheeler (UK/India)

Vantrunk was selected as the primary cable management supplier by Foster Wheeler (UK) for the Exxon Mobil Singapore Parallel Train (SPT) Project.

The project is located at and integrated with the existing Singapore Chemical Plant on Jurong Island, providing feedstock, operating and investment synergies with both the chemical plant and the Singapore Refinery.

When completed, ExxonMobil’s largest owned and operated petrochemical complex and the Corporation's largest integrated chemical and refining site will be located in Singapore. The Project is one of the largest petrochemical projects ever undertaken in Singapore.

ExxonMobil Asia Pacific awarded Foster Wheeler the EPC Contact for the Petrochemical Complex back in 2007 after Foster Wheeler had performed the FEED Phase of the project prior the EPC award.
Foster Wheeler is performing the Engineering, Procurement & Construction for the Aromatics Extraction Unit, an Oxo Alcohol Plant Expansion and Associated Plant Infrastructure. Foster Wheeler executed the project from its UK, Reading Office with support from Foster Wheeler India, Chennai Office

For this Project Vantrunk Supplied it’s internationally acclaimed Speedway Cable Ladder, Vantrunk’s Cable Tray System and Steel Framing Systems all in Corten A.

Turkmenistan

Wellhead Platform Lam-C

Wellhead Platform Lam-C
Year
2011
Client
Dragon Oil Ltd
Contractor
ILK Insaat Taah

The Dzheitune (Lam) C platform, delivered in Q1 2012, represents a third new platform to be installed by Dragon Oil...
...since becoming the operator in the Cheleken Contract Area in 2000 and will aid in the continued development of the Western area of the field. The Lam C platform, which will support a jackup rig, has the capacity to drill up to eight wells on the Lam field.

Vantrunk supplied Speedway Cable Ladder and Cable Tray.

FINISHES & MATERIALS :
Stainless Steel 1.4404 Marine Grade.

SPECIAL FEATURES:
Vantrunk Speedway Cable Ladder products were
supplied with the Speedlok integral coupler system
which decreased overall installation time and reduced
the overall weight of the cable management system.

Qatar

EPIC for Instrumentation PCR's within Dukhan Field

EPIC for Instrumentation PCR's within Dukhan Field
Year
2011
Client
Petrogulf
Contractor
Qatar Petroleum / Tadmur Contracting

The scope includes six (6) Plant Change Requests within Dukhan Fields on EPIC basis as follows: 1. 09/01/PNTU: Replace 62-SDV-120 at Station- U & Provide New SDV Tag No. 33-SDV-025 & 33-SDV-026 at UBMS-A. 2. PCR 09/09 ARBD: Time synchronization for DCS, ESD, F&G and other PLCs at RG Plant. 3. PCR 10/01/PW05: Replacement of 45-PCV-0012 at PWI-5. 4. PCR 10/03/KAHS: Minimize RAG flow at KAHS. 5. PCR 11/07/ARBD: Purge Blower Interlock for F-9450, Hot Oil Furnace at gas Recycling Plant. 6. PCR 12/02/JALM: Configure new Orifice Plates in DCS at JALM.

Abu Dhabi

Occidental Mukhaizna LLC

Year
2011
Client
Occidental
Contractor
Oilfields Supply Centre

Project information coming soon.

Kazakhstan

Kashagan Tranche 3

Kashagan Tranche 3
Year
2011
Client
Agip KCO
Contractor
GATE / Tekfen Insaat

Kashagan, an offshore field located at the north of the Caspian Sea, Kazakhstan sector, was discovered in July, 2000. Owned by a group of partners led by Agip, presently Kashagan could prove to be the world's fifth largest oil field. The field, 75 km SSE of Atyrau, lies in just 3.7 m of water. The field holds an estimated 7 billion - 9 billion barrels of recoverable oil resources and total geological reserves of 38 billion barrels.

A Power Plant has been provided as part of the Onshore Processing Plant to provide electrical power to be used by the Onshore Processing Facility (OPF), Eskene West Railway Project (EWRP) and early works camp. The Power Plant includes 110kV outdoor open terminal switchyard and 35kV and 10kV switchgear to facilitate distribution of electrical power. It will also include LV switchgear for turbine auxiliaries and other required supplies. In addition, provision is to be made for connection to overhead 110kV lines which are tied to the Kazakh National Grid system to allow import and export of electricity.

Heavy duty industrial turbines in the 35-45MWe (ISO) range have been used on this project. The Power Plant has been designed as a manned facility, which can initially operate independently from the OPF. A building will be designed and constructed, sized for three Essential Diesel Generators, together with its day tank and pumps. Three Essential Diesel Generators rated 6.5 MVA, 10 kV, 50 Hz, 1000 rpm shall be installed as part of Tranche 3.
 

Venezuela

Bachaquero & Tamara

Year
2011
Client
Ferrostaal ProCon de Venezuela C.A
Contractor
FMT / KWx

Ferrostaal ProCon de Venezuela C.A., in cooperation with their international and local partners, have put into effect a contract to build two Combined Cycle Power Plants in Zulia state. The Tamare and Bachaquero power plants, that constitute the largest gas and steam power plant project in the history of the operator ENELVEN, are designed to feed 495 megawatts and 525 megawatts, respectively, into the country’s energy system and secure the power supply of the whole region.

Qatar

EPIC for Produced Water Treatment & Injection Phase 2

EPIC for Produced Water Treatment & Injection Phase 2
Year
2010
Client
Qatar Petroleum
Contractor
Black Cat Engineering & Construction

The multidiscipline project is for Produced Water Treatment & Injection (Dukhan Fields: KN, FS, FM & JALEHA Degassing Stations and PWI Stations PS-2, 4, 6, 8 & 9) Phase-2. Vantrunk supplied their Heavy Duty cable tray system in a high silicon structural steel. Th eproject was supplied through our partners in Qatar, Petrogulf.

Qatar

EPIC of EMC Systems for Oryx GTL

Year
2010
Client
Oryx GTL
Contractor
Petroserve Via Petrogulf

Project information coming soon.

Qatar

Oryx GTL Hydrogeneration Plant

Year
2010
Client
Oryx Petroleum
Contractor
DOPET (Doha Petroleum Construction Co. Ltd Via Petrogulf

Project information coming soon.

Qatar

Jet Fuel Pipeline

Year
2010
Client
Qatar Petroleum
Contractor
DOPET (Doha Petroleum Construction Co. Ltd Via Petrogulf

Project Information coming soon.

Qatar

Qatar Gas Maintenance

Year
2010
Client
Qatar Gas
Contractor
DESON Engineering Via Petrogulf

Project Information coming soon.

Azerbaijan

Chirag Oil Project

Chirag Oil Project
Year
2010
Client
AIOC/BP
Contractor
KBR

The $6 billion development plan is the next major step in the ongoing development of the ACG field in the Azerbaijan sector of the Caspian Sea.

The project is planned to increase oil production and recovery from the ACG field through a new offshore facility which is designed to fill a critical gap in the field infrastructure between the existing Deepwater Gunashli (DWG) and Chirag-1 platforms.

Some $4 billion of the total project value will be spent on the construction of facilities and the pre-drill programme, and the balance of the sum will be spent on the platform development well drilling during the production period.

First oil from the Chirag Oil Project, the latest stage in ACG’s development stretching back more than 15 years, is expected in late 2013. 

Qatar

GSVC

Year
2009 - 2010
Client
Qatar Petroleum
Contractor
Larsen Toubro (L&T) Via Petrogulf

Project information coming soon.

Qatar

SGTP

Year
2009 - 2010
Client
Qatar Petroleum
Contractor
Punj Lloyd Via Petrogulf

Project information coming soon.

Qatar

SGTP (HVAC Work)

Year
2009 - 2010
Client
Qatar Petroleum
Contractor
Blue Star Via Petrogulf

Project information coming soon.

UK

Vivergo Fuels

Year
2009
Client
Vivergo Fuels
Contractor
Aker Solutions via R&M

Vivergo Fuels was formed in 2007 as a bio refinery for the future. The exciting new business will help deliver the UK's forecast bio fuel demand once fully operational in 2010.

The plant constructed at Saltend (Hull, Yorkshire) will take over one million tonnes of animal feed wheat each year and with this create two main products: bio ethanol and animal feed.

Vantrunk supplied its cable management products in Corten A to the project via R&M.Vivergo Fuels

Ghana

Jubilee Field

Year
2009
Client
N/A
Contractor
SOFEC

The project will be brought on-stream via a FPSO and 15 subsea production and injection wells, which could rise to as many as 60 or more depending on the success of further appraisal drilling. More than one FPSO may also be used on the field in the future.

Jubilee's reserves most likely stand at about 500 million barrels with the potential to hold up to 1.8 billion barrels of 37-degree API crude.

Phase 1: FPSO in 1100m of water at Jubilee will be capable of processing more than 120,000 bpd of oil, 160 Mmscfd of produced gas, and injecting 230,000 bpd of water. Storage capacity up to 2 million barrels. Gas and water will be re-injected. FPSO will be a conversion, using SOFEC External turret as its mooring type. Production on the field is due to commence in 2010.

Vantrunk Supplied its Speedway SW6 Cable Ladder in Stainless Steel to the Jubilee Project Via Eutex International.

Brazil

Roncador Field Development Phase 3/P-55

Year
2009
Client
Petrobras
Contractor
Quip Consortium Via Polar

Project information coming soon.

Qatar

Qatar Gas Work Shop

Year
2008 - 2009
Client
Qatar Gas
Contractor
MIDGULF Construction Via Petrogulf

Project information coming soon.

UK

Isle of Grain - Power Plant

Year
2009
Client
Total
Contractor
Alstom

Project information coming soon.

Qatar

DUPRP Project

Year
2008 - 2009
Client
Punj Lloyd
Contractor
Petrogulf

Project information coming soon.

Qatar

MPPL Project

Year
2008 - 2009
Client
Qatar Petrolium
Contractor
Petrogulf

Project information coming soon.

Tunisia

British Gas

Year
2008 - 2009
Client
ODE
Contractor
R&M Electrical

Project information coming soon.

Libya

Faregh Project

Year
2008 - 2009
Client
Waha Oil Company
Contractor
PSM

Project information coming soon.

Egypt

BP Rehabilitation Project

Year
2008 - 2009
Client
Dron & Dickson
Contractor
Dron & Dickson

Project information coming soon.

UK

Isle of Grain

Year
2008
Client
BP
Contractor
Watson Norrie

Isle of Grain Project is a multi stage LNG project located at the Isle of Grain, Kent UK.

For the Isle of Grain Project Vantrunk Supplied 316 Grade Stainless Steel Intelok Channel, Bracketry and Cantilevers. Vantrunk Also Supplied its Cable Tray System.

Yemen

LNG Project

Year
2008
Client
Yemen LNG
Contractor
Toyo Kanetsu KK

The Yemen LNG Project comprised of new and existing upstream gas processing facilities including a transfer line linking the two gas processing units, a new main pipeline, which will connect the gas processing facilities to the new liquefaction facilities in Balhaf, and a spur line to transport domestic gas to the Ma’bar area.

Vantrunk worked with Toyo Kanetsu KK on the 420 Million Cubic Feet/Day Gas Processing Plant to serve the near by Yemen LNG Export Terminal.

Vantrunk Supplied SW6 Mild Steel Hot Dip Galv Speedway Cable Ladder and Extra Heavy Duty Cable Tray.

Kazakhstan

Bateman Utilities

Year
2007 - 2008
Client
Bateman Eurasia GmbH
Contractor
AGIP KCO

Supply of Speedway SW6 and 100mm extra heavy duty cable tray, all Corten A deep galvanized finish, for the Utilities Project.

Egypt

Saqqara

Year
2006 - 2008
Client
GUPCO (BP & Egyptian General Petroleum Corporation)
Contractor
KBR - Supplied via R&M

Speedway SW6 stainless steel cable ladder for offshore use and Speedway SW6 Corten A, deep galvanized finish, cable ladder for onshore use.

The Saqqara project is located in the Gulf of Suez, and is operated through GUPCO, BPs JV with the Egyptian General Petroleum Corporation. The project will produce from a 9-slot wellhead tower, and multi-phase fluids will be exported to a dedicated onshore separation and gas processing plant. First production is expected in early 2008.
 

Ireland

Irish Cement - Drogheda Ireland

Year
2008
Client
Kirby Electrical
Contractor
Uni-Trunk

Project information coming soon.

Ireland

Aghada Power Station Cork Ireland

Year
2008
Client
Kirby Electrical
Contractor
Uni-Trunk

Project information coming soon.

Egypt

Apache/Khalda Petroleum Northern Pipe Line Compression Project

Year
2008
Client
JP Kenny
Contractor
R&M Electrical

Project information coming soon.

Norway

Statoil CHP Plant Mongstad

Year
2008
Client
Dong Energy
Contractor
NEM Via KWx

Project information coming soon.

Saudia Arabia

Sharq III Phase 2

Year
2008
Client
Shaw Stone & Webster
Contractor
R&M

Project information coming soon.

Saudia Arabia

Sharq III

Year
2007 - 2008
Client
Shaw Stone & Webster
Contractor
R&M

Project information coming soon.

Kazakhstan

Karachaganak 4th Sweetening Train Strut

Year
2008
Client
Petroface UAE
Contractor
Petroface UAE

Project information coming soon.

Kazakhstan

Karachaganak 4th Sweetening Train

Year
2007
Client
Karachaganak Petroleum Operating B.V (KPO)
Contractor
Petrofac

Supply of Galvanized Structural Steel Speedway SW6 cable ladder and heavy duty cable tray to Petrofac, the international oil and gas facilities service provider, for the Karachaganak 4th Stabilization and Sweetening Train Project.

The Karachaganak Field is located in the Uralsk Region of West Kazakhstan. The Field is one of the world's largest gas condensate fields and is estimated to contain 1.236 billion tonnes of liquids and 1.371 trillion cubic metres of gas in place (17.78 billion barrels of oil equivalent).

The project is aimed at increasing the capacity of the existing Karachaganak Processing Complex (KPC) facilities by the
addition of a fourth train.

Algeria

Sonatrach Boiler Upgrades

Year
2006 - 2007
Client
Sonatrach
Contractor
Ishikawajima Europe BV

Speedway SW6 stainless steel cable ladder, Speedway SW6 hot dip galvanized cable ladder & hot dip galvanized accessories supplied to Ishikawajima Europe BV for further development of Algerias oil industry.

Hydrocarbons play a crucial role in Algeria's economy, providing approximately 97% of export earnings. Sonatrach is the largest Algerian public company and worldwide is the 11th largest oil consortium. Sonatrach was formed to exploit the hydrocarbon resources of Algeria, encompassing exploration, extraction, transport and refining. Sonatrach has also diversified into petrochemicals and seawater desalination.

Sonatrach subsidiaries include Naftal (for domestic fuel distribution), Numhyd (50% ownership of a joint venture with Tunisia's ETAP) and ALEPCO (joint venture with Libya's National Oil Corporation).

Azerbaijan

ACG Onshore Development

ACG Onshore Development
Year
2002 - 2007
Client
BP
Contractor
Kellog Brown & Root

Azeri Full Field Development - Onshore - Sangachal Terminal - Phases 1, 2 & 3 for AIOC

Engineering & procurement by Kellog Brown & Root.

Products supplied include Speedway stainless steel cable ladder, Vantrunk stainless steel cable tray and stainless steel framing systems.

Products also supplied direct to local contractors.

The Sangachal Terminal is one of the worlds largest integrated oil and gas processing terminals. Located 45km south of Baku in the Garadakh District, the Sangachal Terminal is a vital link in Azerbaijans oil and gas industry.

Still expanding, it is already one of the largest oil and gas terminals worldwide. Construction of the terminal originally started in 1996, with the building of oil receiving, processing, storage and export facilities designed as part of the Early Oil Project (EOP). The first export of oil from the Sangachal Terminal was achieved in October 1997.

The Sangachal Terminal is now being expanded to meet increased production and export requirements associated with further phases of development of the Azeri Chirag Gunashli (ACG) oil field and the Shah Deniz gas field.

Azerbaijan

BTC Pipeline

Year
2002 - 2007
Client
Baku-Tbilisi-Ceyhan Pipeline Company
Contractor
Kellogg Brown & Root

Procurement by Kellogg Brown & Root (KBR)

Speedway SW4 & SW6 stainless steel cable ladder & accessories.

The Baku-Tbilisi-Ceyhan pipeline (BTC pipeline) transports crude petroleum 1,776 km from the Azeri-Chirag-Guneshli oil field in the Caspian Sea to the Mediterranean Sea.

The total length of the pipeline in Azerbaijan is 440 km long, in Georgia it is 260 km long and in Turkey is 1076 km long. It passes through Baku, the capital of Azerbaijan; Tbilisi, the capital of Georgia; and Ceyhan, a port on the south-eastern Mediterranean coast of Turkey, hence its name.

It is the second longest oil pipeline in the world. The first oil that was pumped from the Baku end of the pipeline on May 10, 2005 reached Ceyhan on May 28, 2006.

Ireland

Moneypoint Power Station Eire

Year
2006 - 2007
Client
Kirby Electrical
Contractor
Uni-Trunk

Project information coming soon.

Kazakhstan

Kashagan Power Plant

Year
2006
Client
Agip KCO
Contractor
Bateman Eurasia GmbH

Corten A deep galvanized Speedway SW4 & SW6 cable ladder, heavy duty cable tray & accessories for the Power Plant which forms part of the Kashagan Experimental Programme.

THe Kashagan field is being developed by Agip KCO. Kashagan extends over a surface of approximately 75 km x 45 km and is the largest oilfield discovered in the North Caspian Sea PSA contract area.

Kashagan is being developed in phases. The first phase, currently in execution, is the Experimental Program (EP) which will be followed by the Full Field Development (FFD) program.

Agip KCO operations continue onshore, at Eskene West, 35 km north-east of Atyrau. The works started in 2002 and include two main components: the Early Works program and the construction of an onshore processing plant.

The purpose of the Early Works, completed in December 2005, was to establish infrastructures in support of the main construction activities and the operation of the onshore processing facility where oil and gas will be delivered from offshore via a system of pipelines.

UK

Quinn Barlow Production Facility, Wales

Year
2006
Client
HTE Limited
Contractor
UK Cables Limited

Project information coming soon.

Kazakhstan

Kashagan Barges - Accommodation Modules

Year
2006
Client
Agip KCO - Aker McNulty
Contractor
Power Wholesale Limited

Project information coming soon.

Azerbaijan

AIOC - ACG Full Field Development Phase 3

Year
2005 - 2006
Client
BP
Contractor
Kellogg Brown & Root

Project information coming soon.

Norway

Mosjoen Carbon Plant

Year
2006
Client
Bechtel
Contractor
Wesco

Project information coming soon.

Kazakhstan

Agip KCO Kashagan Power Plant

Year
2006
Client
Bateman Eurasia GmbH
Contractor
Bateman Eurasia GmbH

Project information coming soon.

UK

Britannia Satelites Development Project

Year
2005
Client
Conoco Phillips and Chevron Texaco
Contractor
AMEC - Supplied via D&D.

Britannia is one of the largest gas and gas condensate fields to be developed in the North Sea in recent years and was discovered in the mid 1970s

It is the first in the UK sector of the North Sea to be operated jointly by two companies, Conoco and Chevron, through the formation of the new operating company, Britannia Operator Limited.

Gas from Britannia is processed at the Scottish Area Gas Evacuation (SAGE) terminal in St Fergus, which handles gas produced from a number of other North Sea fields.

Images Courtesy AMEC

Azerbaijan

Shah Deniz Offshore

Year
2005
Client
BP
Contractor
Technip

The Shah Deniz (translated to mean the "King of the Sea") gas-condensate field is located in the Azerbaijan sector of the South Caspian Sea, approximately 100km south of Baku. British Petroleum (BP) is the single operator on behalf of a Production Sharing Agreement (PSA) between the State Oil Company of Azerbaijan Republic (SOCAR) and a number of Foreign Oil Companies (FOCs).

The field will be developed in four stages. Stage one "Shah Deniz Gas Export Project" will focus on the eastern flank of the reservoir with a fixed platform in 105m water depth. The fixed platform will be tied back to an onshore terminal at Sangachal via separate gas and gas condensate subsea pipelines. After onshore processing, gas will be exported to markets primarily in Turkey but also in Georgia and Azerbaijan.

Technip Paris is contracted to complete the design, engineering, procurement, assembly, installation, hook up and project management of the production platform: a TPG 500 selfinstalling jack-up, which is a Technip proprietary concept. Installation is scheduled for April 2006.

Images BP p.l.c.

UK

Ineos Chlor

Year
2005
Client
N G Bailey
Contractor
Boultings

Project information coming soon.

Qatar

Oryx GTL Plant Ras Laffan

Year
2005
Client
Air products
Contractor
Air products

Project information coming soon.

Azerbaijan

Shaz Deniz Offshore

Year
2005
Client
Technip
Contractor
Technip

Project information coming soon.

Kazakhstan

PetroKazakhstan (Akshabulak Oil Field)

Year
2005
Client
R&M Export
Contractor
R&M Export

Project information coming soon.

Sudan

Petrodar Operating Company

Year
2005
Client
Bentini-Namfatt Energy JV
Contractor
Bentini-Namfatt Energy JV

Project information coming soon

Qatar

Qatar Petroleum NGL4

Qatar Petroleum NGL4
Year
2003 - 2004
Client
Qatar Petroleum
Contractor
Samsung Corporation

The fourth Natural Gas Liquids Plant (NGL-4) Project is a highly complex, technically challenging development, involving both green and brown field construction work spread over both Dukhan and Mesaieed in Qatar.

Qatar Petroleum awarded a fast-track Lump Sum Engineer/Procurement/Construction & Commissioning (EPIC) contract to a Joint Venture of Snamprogetti, Italy, and Samsung Engineering & Construction Co Ltd, Korea, on the 16th August 1999.

The main products of the 2-billion Qatari Riyals plant are 3,200 TPD of Ethane, 3,000 TPD of Propane, 2,100 TPD of Butane, 780 TPD of NGL Condensate. The ethane produced by the plant will be used as ethane feedstock for Q-Chem plant and QAPCO. The propane is stored in a new 58,000m2 storage tank (T9), similar in design to the existing two tanks. The Butane and NGL Condensate is stored in the existing storage tanks.

Stringent environmental constraints have been applied throughout the development of the NGL-4 Plant has a number of features designed to protect the environment and allow it to fully comply with the State of Qatar's environmental emissions regulations.  

Kazakhstan

SGP & SGI

Year
2004
Client
Tengizchevroil
Contractor
R&M Export

Project information coming soon.

Saudia Arabia

Kindasa Water Services LLC

Year
2004
Client
Weir Westgarth
Contractor
Weir Westgarth

Project information coming soon.

Azerbaijan

BTC Pipeline - Office Facilities

Year
2004
Client
Petrofac International
Contractor
Petrofac International

Project information coming soon.

Qatar

Qatar Petroleum EPIC LPG Tanks

Year
2003 - 2004
Client
Samsung Corporation
Contractor
Samsung Corporation

Project information coming soon.

Algeria

In Salah Gas project

Year
2002 - 2003
Client
M.W. Kellogg Limited
Contractor
MacLean Electrical

In Salah Gas project is a joint development between BP and Sonatrach, the Algerian state energy company.

In Salah Gas is the largest dry gas joint-venture project in the country. The project initially entails the development of three proven gas fields at Krechba, Tegentour, and Reg, located in the remote Saharan desert of southern Algeria. The gas is transported aMacLean Electricallong a series of infield pipelines to the project's central processing facility at Krechba, and then along a 500-kilometre export pipeline to Sonatrach's gas hub and collection point at Hassi R'Mel. By the end of this year gas deliveries will plateau at 9 billion cubic metres of gas per year, increasing Algerian gas exports by about 15 per cent.

In Salah is also the world's first full-scale carbon dioxide capture project at a gas field. Around 1 million tonnes of CO2 will be injected into the reservoir each year.

Vantrunk Supplied its Speedway Cable Ladder, Cable Tray and Steel Framing System to this project.

Russia

Kharyaga Field Phases 1 & 2

Year
1998 - 2003
Client
Total Exploration Russia
Contractor
Petrofac

The Kharyaga Field is located in the North West of the Russian Federation in the Nenets Autonomous District (Okrug). Kharyaga Field is a part of the Timan-Pechora Basin and situated 60km North of the Arctic Circle.

The Kharyaga field is developed in stages according to the terms of the Production Share Agreement (PSA). The investors are Total Exploration Production (TEPR) 40%, Statoil 30%, Zarubezhneft 20% and Nenets Oil Company (NOC) 10%. TEPR is the operator.

Oil production commenced in 1999, with Phase 1 production of 10,000 bbl per day utilising three existing wells. Phase 2 was launched in 2000 to increase oil production and develop additional reserves. An additional 11 wells were drilled during this phase. Phase 3 started in 2007 and at present the production has increased by 50% up to 30,000 bbl per day. This phase involves drilling of more production and injection wells, a process upgrade and installation of gas treatment facilities in order to sale gas and terminate flaring.

Vantrunk Supplied Stainless Steel Cable Management Systems to the first two stages of this project.

UK

Royal Bank of Scotland HQ

Year
2003
Client
A S Neil/Forth Electrical Services
Contractor
MACE Ltd

Project information coming soon.

UK

Buxton Cement

Year
2002 - 2003
Client
Bancroft Electrical & Mechanical
Contractor
EI WHS

Project information coming soon.

Abu Dhabi

ADDIA

Year
2002 - 2003
Client
Abu Dhabi National Oil Company
Contractor
Electromec

Project information coming soon.

UK

Sullom Voe Terminal

Year
2002
Client
BP
Contractor
AMEC

The Sullom Voe Terminal is located at the northern end of the largest of the Shetland Islands. It is also one of
the largest oil and liquefied gas terminals in Europe.

Its main purpose is to act as a buffer between the producing fields offshore and tankers waiting to ship oil to refineries worldwide. The terminal has been designed to allow continuous production offshore, even in bad weather.

Vantrunk Supplied its steel cable management products and asociated support systems to this project.AMEC

UK

BNG Technology Centre

Year
2001 - 2002
Client
British Nuclear Group
Contractor
AMEC

Between 2001 and 2002 Vantrunk Limited supplied its cable management systems to the BNFL Technology Centre at Sellafield Cumbria. The centre comprises integrated state of the art facilities fully supporting activities of scientists, engineers and technologists.

For this project Vantrunk Limited provided pioneering and cost effective engineering solutions to suit the requirements of the client and engineering contractor.

Vantrunk Limited designed and manufactured a bespoke cable ladder system which did not have any slotting to ensure no components fell into the high tech laboratories or radioactive areas

The Ladder System was fully enclosed with Close Fitting Speedway Covers on both the top and the bottom of the Speedway Cable Ladder offering complete mechanical and environmental protection.

Vantrunk designed and manufactured a unique Cable Tray Design for this project which included a special return flange design and an internal heavy duty coupler mechanism.

Kazakhstan

PetroKazakhstan (Hurricane Hydrocarbons)

Year
2002
Client
Tengizchevroil
Contractor
R&M Export

Project information coming soon.

UK

BTC Project BNFL Sellafield

Year
2001 - 2002
Client
AMEC
Contractor
AMEC

Project information coming soon.

UK

BP Magnus Sullom Voe

Year
2001
Client
AMEC
Contractor
Wellhead Electrical/Dron & Dickson

Project information coming soon.

Qatar

Elf Halul Power Project

Year
2001
Client
Elf Petroleum
Contractor
Qatar Kentz

Project information coming soon.

UK

Phillips Jade Offshore Platform

Year
2000 - 2001
Client
Heerema
Contractor
EI-WHS

Project information coming soon.

UAE

Borouge Polyethelene Plant

Year
1999 - 2001
Client
Bechtel/Snamprogetti
Contractor
MacLean Electrical

Project information coming soon.

Qatar

Qatar Vinyl Co Plant

Year
2000
Client
QVC/CCC
Contractor
Petrotec

Project information coming soon.

UK

South Morecambre Onshore Compression Project

Year
2000
Client
British Gas/Halliburton
Contractor
MacLean Electrical

Project information coming soon.

UK

Elgin/Franklin Offshore Platform

Year
1998 - 2000
Client
Elf Petroleum
Contractor
MacLean Electrical

Project information coming soon

Ireland

Dunboyne Power Station

Year
2000
Client
Kirby Electrical
Contractor
Uni-Trunk

Project information coming soon.

Ireland

Xerox Plant

Year
2000
Client
Xerox
Contractor
Uni-Trunk

Project information coming soon.

Tunisia

Hannibal Gas Plant

Year
2000
Client
British Gas
Contractor
Costain

Project information coming soon.

Oman

LNG Plant

Year
1999 - 2000
Client
Chiyoda/Foster Wheeler
Contractor
Bahwan Engineering

Project information coming soon.

Jordan

Magnesium Dioxide Plant

Year
2000
Client
Atlilla Dogan, Turkey
Contractor
Atlilla Dogan, Turkey

Project information coming soon.

Kazakhstan

Karachaganak (Main Phase)

Year
1999 - 2000
Client
Bechtel
Contractor
Bechtel

Project information coming soon.

UK

Captain Offshore Field Expansion

Year
1999
Client
Texaco
Contractor
Kvaerner Oil & Gas

Project information coming soon.

UK

Shearwater Offshore Platform

Year
1998 - 1999
Client
Shell/Esso
Contractor
AMEC

Project information coming soon.

Qatar

Dukhan Project

Year
1998 - 1999
Client
QGPC
Contractor
Petrotec

Project information coming soon.

Canada

Sable Island Offshore Platforms

Year
1999
Client
Kvaerner Oil & Gas
Contractor
Kvaerner Oil & Gas

Project information coming soon.

UAE

Taweelah B Power Station

Year
1998 - 1999
Client
Eastern Bechtel
Contractor
Easter Bechtel

Project information coming soon.

Kazakhstan

Karachaganak (Initial Phase)

Year
1998
Client
Bechtel
Contractor
MacLean Electrical

Project information coming soon.

UK

Brent Offshore Field Redevelopment

Year
1997 - 1998
Client
Shell/Esso
Contractor
AMEC

Project information coming soon.

Russia

Karyagah Project

Year
1998
Client
Halliburton
Contractor
MacLean Electrical

Project information coming soon.

UK

Glas Dowr FPSO

Year
1998
Client
Bluewater
Contractor
Bluewater

Project information coming soon.

UK

Bideford Dolphin Drill Rig

Year
1998
Client
Harland & Wolff Shipyard, Belfast
Contractor
Harland & Wolff Shipyard, Belfast

Project information coming soon.